Footfall during roadworks: tracking a street while it is dug up
How to measure footfall during roadworks on a shopping street: set a baseline, pick a comparison street, read the weekly change, and keep evidence for the council.
Part of the guide Location intelligence automation
To track footfall during roadworks, measure the same small area in front of the affected shops every week, compare it with a similar street nearby that is not being dug up, and keep the series from before the works start until after the barriers come down. The difference between the two streets, week by week, is the closest honest picture of what the works cost the street in presence. A single before and after figure is not enough, because seasons, holidays and weather move both streets at once.
This is for shop owners and their associations, town centre managers, landlords with tenants on a works route, and councils that want to show traders what is happening. It explains how to set up the measurement, a made-up example of a tram line rebuild, the traps, and an AI employee that does the weekly reading and sends it to everyone who needs it.
Why a comparison street matters
Presence on any street rises and falls for reasons that have nothing to do with diggers: school holidays, a heatwave, a payday weekend, a festival two districts away. If you only watch the street under works, every one of those swings looks like an effect of the works. Watch a second street with a similar mix of shops at the same time, and the swings they share cancel out. What is left, the gap that opens between them, is the part you can reasonably put down to the works.
Choose the comparison street with care: same kind of shops, a similar distance from the centre, no works of its own and not on a diversion route. A diversion route is the classic trap, because it gets busier precisely because of the works, and makes the drop look larger than it is.
Setting up the measurement
- List three to five points along the street under works, at the shop fronts that matter, and two or three points on the comparison street.
- Use the Mobility Footfall block with a small radius, 100 to 200 m, so each point reads its own stretch of pavement and not the whole district.
- Read the last 7 days every week, with Footfall, Busy hours and Trend switched on.
- Keep every week's reading in a table or sheet, one row per point per week, so you build a series rather than a snapshot.
- Add the roadworks themselves: Traffic incidents around each point tells you which weeks the works and closures were actually present.
A made-up example: a tram line rebuild
The figures are invented. A traders' association on a shopping street in Lisbon learns that the tram tracks will be replaced over ten weeks, with one side of the street fenced off at a time. They pick four points on the street and three on a parallel street with similar shops. For the three weeks before work starts, both streets move together. In the first week of works the street under works falls 18% against its own baseline while the comparison street falls 4%, because of a rainy week. The gap, about 14 points, is the figure they take to the council.
| Week (made up) | Works street vs baseline | Comparison street vs baseline | Gap |
|---|---|---|---|
| Before works | 0% | 0% | 0 |
| Works week 1 | -18% | -4% | -14 |
| Works week 4, fence on the north side | -22% | +2% | -24 |
| Works week 8, fence moved south | -9% | +1% | -10 |
| Two weeks after | -3% | 0% | -3 |
Invented figures to show how the weekly gap is read.
Two details come out of the hour-by-hour split. The drop is deepest in the evening, when the fence blocks the lit side of the street, and the busiest day moves from Saturday to Sunday while a Saturday market is suspended. Both are things the association can act on: later lighting along the hoarding, and asking the market to come back early.
Mistakes that weaken the evidence
- One reading before, one after. Without the weekly series you cannot separate the works from the season.
- A circle too wide. At 500 m the reading takes in side streets and squares the works do not touch, and the effect fades into the average.
- Calling people-hours customers. Fewer people-hours on the pavement is a strong signal, but it is not lost sales. Put till figures next to it when you have them.
- Forgetting the delay. The figures for this week arrive in about ten days. Plan the weekly email on that rhythm and do not expect the first week of works to show at once.
- Ignoring the end. Keep measuring for a month after the barriers go. A street that does not recover is a different conversation from one that bounces back.
Letting an AI employee keep the weekly log
In xMap Flows the weekly reading can run by itself and land with every trader on the list. It fits the wider practice described on location intelligence automation: data that arrives on a timetable, read the same way each time.
- Schedule: every Monday at 09:00.
- My data: the table of points, each marked works or comparison.
- Mobility Footfall: radius 150 m, last 7 days, Footfall, Busy hours and Trend.
- Traffic incidents: around each incoming place, so each point says whether works were nearby that day.
- Calculated field: the change against each point's baseline, typed once as a formula.
- xMap LLM: a short paragraph on the gap between the two streets and what moved in the busy hours.
- Email: to the association's members and the council contact.
Each Monday the members get the week's figures for every point, whether works were present, the gap against the comparison street and a few plain sentences. Over the life of the works that becomes a record nobody had to assemble by hand.
Questions
Can footfall data prove that roadworks cost a shop money?
It can show that presence on the street fell more than on a similar street at the same time. Lost sales need the shop's own takings beside it; the two together make a strong case.
How soon after works start will I see the effect?
Each day's footfall arrives about 10 days later, so the first week of works appears in the reading roughly ten days after it ends.
What radius should I measure on a narrow street?
Use 100 to 200 m. Up to 200 m the block reads the single small cell the point sits in, which keeps side streets out of the figure.
Does it work for works that started before the data begins?
The data starts on 17 October 2026, so no baseline exists before that. You can still track the rest of the works and the recovery afterwards against a comparison street.